22/07/2010

€350m Poolbeg Incinerator Halted

Construction has halted on Dublin's Poolbeg incinerator after the Department of the Environment failed to approve a foreshore licence.

The Department is yet to process an application lodged in December 2008 for an out-flow pipe into the sea.

Work on the €350m facility can't resume until the license is granted.

Incinerator operator Covanta are seeking a meeting with Taoiseach Brian Cowen.

The Environment Minister John Gormley, who has said he would prefer mechanical biological treatment to deal with the waste problem than the incinerator which would be located in his constituency, recently published draft policy proposals which would make the project economically unviable.

The President of Europe arm of the company, Scott Whitney, said they will not rule out legal action against Ireland if the project is shelved.

He said the firm has spent of millions of euro on the project to date and that up to 600 jobs would be lost if the project is scrapped.

(GK)

Related Irish News Stories
Click here for the latest headlines.

26 March 2024
Environmental Report Highlights 'Failure To Act'
A new environmental report highlights Northern Ireland's failure to act on protecting its environment, Alliance's Environment spokesperson John Blair MLA has said.
07 August 2014
DCC Urged To Terminate Poolbeg Incinerator Project
Dublin City Council's Chief Executive, Owen Keegan, has been urged to end the contract for the construction of the Poolbeg Incinerator. The Chief Executive had previously said that a decision on the incinerator would be made following an EU ruling on two complaints made about the project.
07 May 2014
Poolbeg Incinerator Did Not Break State Aid Rules - Eu Commission
The European Commission has ruled that the Poolbeg Incinerator project did not breach rules on state aid, and will continue on market terms. However, the project is still facing a second complaint over public procurement procedures, and will be cancelled should the ruling go against it.
08 January 2014
Minister Urges Govt To Take Health Concerns Surrounding Eirgrid Project Seriously
Sinn Féin's EU candidate for the constituency of Ireland South, Liadh Ní Riada, has today called on the government to take the health concerns surrounding the EirGrid Grid Link project seriously.
11 January 2010
Incinerator Still Inflames Community
As many as 500 construction jobs may be in doubt as the building of a highly controversial 600,000 tonne waste incinerator in Dublin's Poolbeg continues to be debated. It has now emerged that any so-called interference with the project could leave the Irish State facing a multimillion euro compensation bill.